10/11/22 – US 31W Construction Update

ELIZABETHTOWN, Ky. (October 11, 2022) The contractor has finished the outside northbound and southbound work, and has now started the median work, which is the final phase of construction.  Work is anticipated to be completed by November 15, at which time the final traffic configuration will be in place.  From now until November 15 (at the latest), the median will be closed between the signal at Diecks Drive/Cardinal Drive and the signal at the US31W Bypass.  During this time, no left-turns will be permitted in between the two signals.  Anyone looking to make a left turn in this stretch will need to make a U-turn movement at the traffic signals (Diecks Drive to the south, and US31W Bypass to the north). 

Contact: Chris Jessie
270-766-5066 (office)
270-619-2577 (cell)
Chris.Jessie@ky.gov